– Total distance executed compromising excavation and all necessary works is: 1.3 Km
– Duration period for project implementation, Testing and Commissioning in spite of terrain difficulties in the RIVER: 48 Days
– 10 days on AIN MANZOUL Road compromising excavation + pipes installation and landfilling and remaining 38 days in river where a complete concrete structure with iron beams were implemented for pipes protection

Day 40 - 1-9-2018

River

Day 41 - 2-9-2018

River

Day 42 - 3-9-2018

River

Day 43 - 4-9-2018

River

Day 44 - 5-9-2018

River

Day 45 - 6-9-2018

Road

Day 46 - 13-9-2018

Road

Day 47 - 14-9-2018

Road

Day 48 - 15-9-2018

Road