– Total distance executed compromising excavation and all necessary works is: 1.3 Km
– Duration period for project implementation, Testing and Commissioning in spite of terrain difficulties in the RIVER: 48 Days
– 10 days on AIN MANZOUL Road compromising excavation + pipes installation and landfilling and remaining 38 days in river where a complete concrete structure with iron beams were implemented for pipes protection