– Total distance executed compromising excavation and all necessary works is: 1.3 Km
– Duration period for project implementation, Testing and Commissioning in spite of terrain difficulties in the RIVER: 48 Days
– 10 days on AIN MANZOUL Road compromising excavation + pipes installation and landfilling and remaining 38 days in river where a complete concrete structure with iron beams were implemented for pipes protection

Day 1 - 18-7-2018

River

Road

Day 2 - 19-7-2018

River

Road

Day 3 - 20-7-2018

River

Road

Day 4 - 21-7-2018

River

Road

Day 5 - 23-7-2018

River

Road

Day 6 - 24-7-2018

River

Road

Day 7 - 24-7-2018

River

Road

Day 8 - 26-7-2018

River

Road

Day 9 - 27-7-2018

River

Road

Day 10 - 28-7-2018

River

Road

Day 11 - 30-7-2018

River

Road

Day 12 - 31-7-2018

River

Road